Job 22138Reference

Atkinson Lane, 78, Watsonville (PV-B)

Exception summary

14 items need attention

7 high-priority items should be resolved before closing.

7

high risk

Report periodAug 2026
System size169.02 kW
Install typePIPE RACK
TeamConnor English · Imani Brown · Jesse Q

Suggested audit note

Awarded

$704,232

CTC

$722,217

Contracted + CO

$727,079

CTC vs Contract + CO

-$4,862

-0.7%

Cost utilization is ahead of completion

medium

97.7% of budget spent at 78.4% completion (19.3% gap).

Next investigation

Confirm remaining committed costs, percent complete, and whether current spending indicates a likely closeout overrun.

Source: CTC Report AF5/P3 and H95:BV97

CTC is below Contract + CO

medium

$4,862 (-0.7%) difference.

Next investigation

Reconcile original contract and all additive/deductive COs; escalate unbilled scope.

Source: SharePoint COs / PVBid

Travel over budget / Per Diem under budget

high

$24,319 travel overrun; $8,128 unused per diem. Combined variance is $16,191.

Next investigation

Confirm whether the crew commuted daily because nearby lodging was unavailable; compare combined Travel + Per Diem actual with budget.

Source: Job Cost Detail / Travel + Per Diem

Labor is over budget

high

$51,416 (32.1%) over budget.

Next investigation

Use the cost-code detail to identify the labor, material, subcontractor, equipment, or other drivers.

Source: CTC Report H95:BV97

Material is under budget (provisional)

low

$49,461 (-20.2%) under budget at 78.4% completion.

Next investigation

Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.

Source: CTC Report H95:BV97

Equipment is over budget

high

$12,375 (171.9%) over budget.

Next investigation

Use the cost-code detail to identify the labor, material, subcontractor, equipment, or other drivers.

Source: CTC Report H95:BV97

Other is under budget (provisional)

low

$25,148 (-47.1%) under budget at 78.4% completion.

Next investigation

Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.

Source: CTC Report H95:BV97

Contingency: unspent / provisional

low

$23,212 variance (-100.0%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

PV Wire and Cable (E): over budget

high

$13,705 variance (39.6%).

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

Project Management by PM: over budget

high

$12,541 variance (158.6%).

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

PV Elec Equip & Installation (E): unspent / provisional

low

$12,368 variance (-14.6%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

PV Conduit and Raceways (E): unspent / provisional

low

$12,268 variance (-37.8%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

Wire HRS/kW is outside the sanity range

high

1.82× budget (1.67 actual vs 0.92 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check

PM hours is outside the sanity range

high

2.08× budget (229.00 actual vs 109.85 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check