Awarded
$69,342
Exception summary
6 high-priority items should be resolved before closing.
high risk
Suggested audit note
Awarded
$69,342
CTC
$69,342
Contracted + CO
$69,342
CTC vs Contract + CO
$0
0.0%
102.4% of budget spent at 72.8% completion (29.6% gap).
Next investigation
Confirm remaining committed costs, percent complete, and whether current spending indicates a likely closeout overrun.
Source: CTC Report AF5/P3 and H95:BV97
$11,958 (80.7%) over budget.
Next investigation
Use the cost-code detail to identify the labor, material, subcontractor, equipment, or other drivers.
Source: CTC Report H95:BV97
$2,665 (-15.0%) under budget at 72.8% completion.
Next investigation
Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.
Source: CTC Report H95:BV97
$3,261 (-99.4%) under budget at 72.8% completion.
Next investigation
Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.
Source: CTC Report H95:BV97
$3,605 (-47.7%) under budget at 72.8% completion.
Next investigation
Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.
Source: CTC Report H95:BV97
$5,238 variance (232.8%).
Next investigation
Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.
Source: Job Cost Detail / PVBid
$3,065 variance (-39.4%).
Next investigation
Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.
Source: Job Cost Detail / PVBid
$2,618 variance (-91.5%).
Next investigation
Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.
Source: Job Cost Detail / PVBid
$2,388 variance (-56.2%).
Next investigation
Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.
Source: Job Cost Detail / PVBid
$2,266 variance (-100.0%).
Next investigation
Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.
Source: Job Cost Detail / PVBid
$1,575 variance (77.2%).
Next investigation
Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.
Source: Job Cost Detail / PVBid
3.34× budget (2.84 actual vs 0.85 budget).
Next investigation
Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.
Source: PVBid / CTC sanity check
2.64× budget (3.40 actual vs 1.29 budget).
Next investigation
Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.
Source: PVBid / CTC sanity check
1.78× budget (31.75 actual vs 17.80 budget).
Next investigation
Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.
Source: PVBid / CTC sanity check
2.86× budget (99.00 actual vs 34.61 budget).
Next investigation
Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.
Source: PVBid / CTC sanity check