Job 23122Reference

Harrison St, 988, San Francisco (JS Sullivan) PV

Exception summary

10 items need attention

2 high-priority items should be resolved before closing.

2

high risk

Report periodJul 2026
System size21.60 kW
Install typePIPE RACK
TeamConnor English · Ian Hoffbeck · Tim McKeever

Suggested audit note

Awarded

$95,809

CTC

$97,965

Contracted + CO

$99,809

CTC vs Contract + CO

-$1,844

-1.8%

Cost utilization is ahead of completion

high

100.1% of budget spent at 85.1% completion (15.0% gap).

Next investigation

Confirm remaining committed costs, percent complete, and whether current spending indicates a likely closeout overrun.

Source: CTC Report AF5/P3 and H95:BV97

CTC is below Contract + CO

medium

$1,844 (-1.8%) difference.

Next investigation

Reconcile original contract and all additive/deductive COs; escalate unbilled scope.

Source: SharePoint COs / PVBid

Labor is over budget

medium

$3,422 (14.9%) over budget.

Next investigation

Use the cost-code detail to identify the labor, material, subcontractor, equipment, or other drivers.

Source: CTC Report H95:BV97

Equipment is under budget (provisional)

low

$3,280 (-100.0%) under budget at 85.1% completion.

Next investigation

Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.

Source: CTC Report H95:BV97

Materials Handling / Daily Management: unspent / provisional

low

$3,111 variance (-80.4%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

Permitting / Inspections: over budget

medium

$3,034 variance (127.4%).

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

Commission / Bonus: over budget

medium

$2,107 variance.

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

PV Conduit and Raceways (E): unspent / provisional

low

$1,788 variance (-106.7%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

Conduit HRS/kW is outside the sanity range

medium

0.13× budget (0.09 actual vs 0.67 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check

Supervision hours is outside the sanity range

high

1.92× budget (54.14 actual vs 28.16 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check