Job 23176Reference

Alum Rock Ave, 1860, San Jose – PV

Exception summary

14 items need attention

7 high-priority items should be resolved before closing.

7

high risk

Report periodJul 2026
System size85.86 kW
Install typePIPE RACK
TeamEric Nyman · Veda Taylor · Jesse

Suggested audit note

Awarded

$352,900

CTC

$359,867

Contracted + CO

$354,999

CTC vs Contract + CO

$4,868

1.4%

Cost utilization is ahead of completion

high

102.2% of budget spent at 82.7% completion (19.5% gap).

Next investigation

Confirm remaining committed costs, percent complete, and whether current spending indicates a likely closeout overrun.

Source: CTC Report AF5/P3 and H95:BV97

CTC is above Contract + CO

medium

$4,868 (1.4%) difference.

Next investigation

Reconcile original contract and all additive/deductive COs; escalate unbilled scope.

Source: SharePoint COs / PVBid

Labor is over budget

high

$37,309 (44.2%) over budget.

Next investigation

Use the cost-code detail to identify the labor, material, subcontractor, equipment, or other drivers.

Source: CTC Report H95:BV97

Equipment is under budget (provisional)

low

$7,840 (-100.0%) under budget at 82.7% completion.

Next investigation

Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.

Source: CTC Report H95:BV97

Other is under budget (provisional)

low

$21,986 (-63.7%) under budget at 82.7% completion.

Next investigation

Treat this as unspent budget until closeout; check remaining commitments and incomplete scope.

Source: CTC Report H95:BV97

Contingency: unspent / provisional

low

$23,329 variance (-100.0%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

PV Wire and Cable (E): over budget

high

$19,420 variance (160.9%).

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

PV Elec Equip & Installation (E): over budget

high

$10,189 variance (40.4%).

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

Rack Building (I): over budget

medium

$9,944 variance (37.4%).

Next investigation

Open Job Cost Detail and confirm labor, material, equipment, or added-scope drivers.

Source: Job Cost Detail / PVBid

PV Modules & Installation (I): unspent / provisional

low

$9,908 variance (-15.2%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

Materials Handling / Daily Management: unspent / provisional

low

$7,839 variance (-68.5%).

Next investigation

Treat this as unspent budget until closeout; confirm remaining commitments, timing, and incomplete scope.

Source: Job Cost Detail / PVBid

Conduit HRS/kW is outside the sanity range

high

1.89× budget (0.83 actual vs 0.44 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check

Wire HRS/kW is outside the sanity range

high

2.67× budget (2.08 actual vs 0.78 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check

Supervision hours is outside the sanity range

high

2.63× budget (141.02 actual vs 53.65 budget).

Next investigation

Confirm the estimating basis in PVBid; ask Greg to review if the budget basis appears incorrect.

Source: PVBid / CTC sanity check